Data as of August 3, 2026

Charging point fleet (IRVE)

The stock of public charging infrastructure in France: how many charging points, how much installed power, where, and what share of fast (DC) charging.

Publicly accessible charging points declared under the IRVE scheme and consolidated by Etalab, excluding the private fleet (home, closed company premises).

Source: Fichier consolidé des bornes de recharge pour véhicules électriques (Etalab)

Charging points

0

Open to the public, all of France

Stations

0

Distinct charging sites

Cumulative power

0 MW

Installed nominal power

Fast-charging share

0.0 %

Charging points on direct current (DC)

The EV fleet versus the fast-charging network

Battery-electric vehicles per public charging point, and per fast charging point (≥ 100 kW).

EVs per charging point

0

Battery-electric fleet ÷ total public charging points

EVs per fast charging point (≥ 100 kW)

0

Battery-electric fleet ÷ charging points ≥ 100 kW

Balance ~100 EVs/point

EV fleet: SDES vintage as of 1 January 2026. Charging points: daily IRVE Etalab snapshot as of August 3, 2026. Publicly accessible charging points only (excludes home and closed-company charging).

Sharp disparities between departments

The same EV / charging point ratio as above, broken down by department: the fast-charging network is not evenly sized against the local EV fleet everywhere.

View data
EVs per fast charging point (≥ 100 kW) ratio by department, 97 departments ranked from highest to lowest. Top five: La Réunion 696 EVs/point, Paris 131 EVs/point, Haute-Corse 119 EVs/point, Hauts-de-Seine 99 EVs/point, Alpes-Maritimes 66 EVs/point.
DepartmentEVs per pointBattery-electric fleetCharging points
La Réunion69615,30522
Paris13138,163291
Haute-Corse1197,15860
Hauts-de-Seine9957,314577
Alpes-Maritimes6634,246516
Corse-du-Sud594,03268
Ardèche576,388113
Haute-Loire493,75376
Creuse421,18528
Yvelines4147,1281,155
Var3528,104793
Gers354,198121
Mayenne355,910169
Bas-Rhin3127,502894
Loire-Atlantique3131,4431,018
Bouches-du-Rhône3057,8851,929
Finistère3019,152637
Tarn308,558283
Rhône2945,6281,558
Haute-Savoie2822,989827
Val-de-Marne2819,400695
Maine-et-Loire2717,095642
Seine-Saint-Denis2719,025701
Gard2619,506762
Isère2630,9821,188
Dordogne267,371282
Lot262,880110
Manche2511,313457
Vendée2515,196611
Ille-et-Vilaine2423,092968
Pyrénées-Atlantiques2413,507566
Ardennes244,182174
Haut-Rhin2319,572855
Gironde2338,2051,685
Aveyron234,293186
Essonne2226,8471,244
Seine-Maritime2225,9641,169
Oise2217,236783
Nord2153,1492,513
Loire2114,144667
Meuse212,602124
Haute-Garonne2037,6371,846
Indre-et-Loire2013,554667
Vaucluse2013,669694
Doubs2010,435533
Jura204,363217
Orne203,427174
Hérault1928,5481,486
Seine-et-Marne1929,9341,586
Val-d'Oise1921,0871,131
Eure1912,360639
Morbihan1914,096747
Hautes-Alpes192,308124
Pas-de-Calais1829,2421,611
Puy-de-Dôme1813,412738
Ariège182,280124
Hautes-Pyrénées183,492198
Cantal181,996114
Haute-Saône183,122175
Alpes-de-Haute-Provence173,486203
Charente-Maritime1713,856827
Loiret1712,985784
Landes179,174534
Côtes-d'Armor1711,053636
Aisne178,333483
Deux-Sèvres175,988357
Lot-et-Garonne166,033369
Haute-Vienne166,676418
Meurthe-et-Moselle1514,7381,008
Moselle1521,9731,419
Charente146,292459
Loir-et-Cher145,599389
Calvados1316,0301,207
Savoie1310,322779
Vienne138,998707
Eure-et-Loir137,792581
Territoire de Belfort132,380189
Vosges136,131459
Tarn-et-Garonne125,730492
Sarthe129,309786
Allier124,749384
Ain1117,1251,493
Marne1110,734974
Pyrénées-Orientales119,527833
Somme118,647793
Nièvre112,496225
Drôme1012,6851,286
Côte-d'Or109,8601,011
Aube105,049516
Corrèze104,248442
Saône-et-Loire109,005944
Cher94,365508
Aude86,621828
Yonne84,867606
Indre72,435352
Lozère7816119
Haute-Marne51,934420

4 department(s) with no charging point at all for the "EVs per fast charging point (≥ 100 kW)" metric (local EV fleet present but no network, ratio not computable): Guadeloupe, Guyane, Martinique, Mayotte.

  • Different reference dates: EV fleet (SDES) as of 1 January, charging points (IRVE Etalab) daily snapshot.
  • Charging points are counted where they are installed: a department crossed by a major motorway corridor mechanically shows a low ratio, without its residents actually being better equipped day to day.
  • 0.9% of the charging points in the consolidated file (2,005 rows) cannot be matched to any department (missing INSEE code and no usable postal code in the address, or Corsica 20xxx which cannot be resolved) and are therefore absent from this ranking.

Regional breakdown of the fleet

Number of charging points and cumulative power by region. Toggle between the two views below.

View data
Regional breakdown of the IRVE charging point fleet by number of charging points: Île-de-France 28,045 charging points, Auvergne-Rhône-Alpes 21,310 charging points, Nouvelle-Aquitaine 19,517 charging points, Occitanie 16,725 charging points, Hauts-de-France 14,810 charging points, Provence-Alpes-Côte d'Azur 12,897 charging points, Grand Est 12,368 charging points, Normandie 10,950 charging points, Pays de la Loire 7,802 charging points, Bretagne 7,550 charging points, Bourgogne-Franche-Comté 7,407 charging points, Centre-Val de Loire 5,710 charging points, Corse 353 charging points, Guadeloupe 141 charging points, Martinique 5 charging points, La Réunion 2 charging points.
RegionCharging pointsStationsCumulative power (kW)ACDC
Île-de-France28,0454,9301,566,08721,0417,004
Auvergne-Rhône-Alpes21,3104,5572,043,63011,4009,910
Nouvelle-Aquitaine19,5174,9531,424,72312,6016,916
Occitanie16,7254,5191,663,2639,9546,771
Hauts-de-France14,8102,9781,318,7688,3026,508
Provence-Alpes-Côte d'Azur12,8973,2171,043,2948,6054,292
Grand Est12,3682,0251,337,2795,1857,183
Normandie10,9502,601774,8017,1503,800
Pays de la Loire7,8022,013693,5084,8082,994
Bretagne7,5501,955632,5304,5103,040
Bourgogne-Franche-Comté7,4071,436810,0893,3824,025
Centre-Val de Loire5,710926686,6232,5083,202
Corse35315929,298213140
Guadeloupe141632,5988457
Martinique536550
La Réunion224420

Source: Fichier consolidé des bornes de recharge pour véhicules électriques (Etalab). Publicly accessible charging points declared under the IRVE scheme and consolidated by Etalab, excluding the private fleet (home, closed company premises).

AC or DC charging?

National breakdown of charging points by current type. A charging point is classed as "fast charging" (DC) if it offers a Combo CCS or CHAdeMO connector.

View data
Breakdown of charging points by current type: Alternating current (AC) 144,591 (63.8 %), Direct current (DC, fast charging) 82,034 (36.2 %).
Current typeCharging points%
Alternating current (AC)144,59163.8
Direct current (DC, fast charging)82,03436.2

Source: Fichier consolidé des bornes de recharge pour véhicules électriques (Etalab). Publicly accessible charging points declared under the IRVE scheme and consolidated by Etalab, excluding the private fleet (home, closed company premises).

Power of charging points

Breakdown of the fleet by declared nominal power bracket, from slow charging (≤ 7,4 kW) to ultra-fast (> 150 kW), independent of current type.

View data
Breakdown of the 226,625 public charging points by power bracket: Lente (≤ 7,4 kW), 33,988 (15.0 %), Accélérée (7,4–22 kW), 85,044 (37.5 %), Rapide (22–150 kW), 66,303 (29.3 %), Ultra-rapide (> 150 kW), 41,290 (18.2 %).
Power bracketCharging pointsShare
Lente (≤ 7,4 kW)33,98815.0 %
Accélérée (7,4–22 kW)85,04437.5 %
Rapide (22–150 kW)66,30329.3 %
Ultra-rapide (> 150 kW)41,29018.2 %

Source: Fichier consolidé des bornes de recharge pour véhicules électriques (Etalab). Publicly accessible charging points declared under the IRVE scheme and consolidated by Etalab, excluding the private fleet (home, closed company premises).

Growth of the fleet over time

Cumulative count of charging points still recorded today, aggregated by declared commissioning year (implausible dates, before 2010, are excluded).

View data
Cumulative charging points commissioned, from 4 in 2010 to 133,828 in 2026.
YearCommissionedCumulative
201044
2012812
2013618
2014332350
2015266616
20169501,566
20171,5533,119
20185143,633
20191,4425,075
20202,4277,502
202112,71720,219
202216,50836,727
202328,51465,241
202430,74695,987
202526,739122,726
202611,102133,828

Source: Fichier consolidé des bornes de recharge pour véhicules électriques (Etalab). Publicly accessible charging points declared under the IRVE scheme and consolidated by Etalab, excluding the private fleet (home, closed company premises).

Monthly national history (Avere-France / Gireve barometer)

The Etalab dataset above is a point-in-time geographic reading. The Avere-France / Gireve national barometer publishes the number of public charge points in France every month. The monthly history is reconstructed here since 2022, together with the usage indicators (availability, sessions, consumption) published from late 2024 onward.

Manual entry: The national monthly history is only published as PDF (the barometer); it is entered by hand from each Avere-France / Gireve barometer (PDFs kept in the repository for audit). The “technical availability rate” is only comparable from late 2024 onward (an earlier, differently-defined indicator is not carried over).
197,663
public charge points (June 2026)
10.3 GW
total installed power (June 2026)
142 GWh
estimated monthly charge-point consumption (June 2026)
View data
Number of public charge points in France, month by month (Avere-France / Gireve barometer), from Jan 2022 to Jun 2026; 197,663 in the latest month.
MonthPublic charge pointsStationsInstalled powerTechnical avail.Sessions / pointTotal consumption
Jan 202254,45821,9701.22 GW
Feb 202255,51522,3131.24 GW
Mar 202257,73222,8701.34 GW
Apr 202260,04023,8601.39 GW
Jun 202264,54625,6241.5 GW
Jul 202266,96026,5151.56 GW
Oct 202275,27928,7371.81 GW14
Nov 202277,31829,3231.89 GW
Dec 202282,10730,3522.12 GW15
Jan 202385,28431,3412.29 GW14.5
Feb 202390,80332,8652.76 GW12.6
Mar 202395,75534,8392.98 GW13.6
Apr 202399,40435,2553.13 GW13.8
May 2023100,59635,7553.22 GW13.8
Jun 2023101,68136,7713.34 GW13.75
Jul 2023104,72337,9893.53 GW16.69
Aug 2023107,93738,7143.64 GW16.7
Sep 2023109,85638,3023.82 GW14.4
Oct 2023111,20938,7244.07 GW15.1
Nov 2023114,38639,3894.08 GW14.1
Dec 2023118,00940,2014.31 GW20
Jan 2024120,35440,8424.49 GW17
Feb 2024123,34741,4174.62 GW14.7
Mar 2024127,28742,3184.77 GW15.7
Apr 2024129,52542,7114.92 GW15.2
May 2024133,05343,4415.2 GW15.7
Jun 2024138,88744,7035.6 GW13.8
Jul 2024143,67845,6465.89 GW16.9
Aug 2024146,77146,4456.06 GW18.4
Sep 2024149,66847,2216.21 GW18.4
Oct 2024150,05247,6286.57 GW94 %17.645.9 GWh
Nov 2024152,88748,3646.71 GW94 %17.947.7 GWh
Dec 2024154,69448,2476.99 GW93 %25.777 GWh
Jan 2025157,34848,8667.13 GW93 %23.371 GWh
Feb 2025159,96349,7317.26 GW93 %20.864 GWh
Mar 2025163,65650,8337.51 GW93 %22.169 GWh
Apr 2025168,05551,4697.72 GW93 %22.475 GWh
May 2025169,10651,6337.85 GW93 %22.475 GWh
Jun 2025169,55951,5687.99 GW92 %23.782 GWh
Jul 2025174,57452,1898.26 GW93 %29.5109 GWh
Aug 2025177,18052,9208.36 GW93 %30.9113 GWh
Sep 2025179,87653,4458.52 GW92 %25.285 GWh
Oct 2025181,02454,5088.71 GW92 %25.491 GWh
Nov 2025184,14153,7448.88 GW93 %2590 GWh
Dec 2025185,50153,8379.18 GW92 %23.695 GWh
Jan 2026189,94354,7069.31 GW91 %28.5110 GWh
Feb 2026190,87853,1319.46 GW91 %26.5137 GWh
Mar 2026192,00853,5569.67 GW90 %29.6151 GWh
Apr 2026194,99654,3309.97 GW90 %32.2147 GWh
May 2026195,35654,57810.12 GW89 %33.2140 GWh
Jun 2026197,66355,06210.34 GW89 %33.1142 GWh

Source: Avere-France / Gireve, Baromètre national des infrastructures de recharge ouvertes au public. Public charge points in France (Décret n°2017-26 definition), Avere-France / Ministry for Ecological Transition barometer, based on Gireve data. The month is the barometer's “as of” reference date.

Main operators

The top twenty charging point operators by volume, each bar broken down by power bracket (the remainder aggregated under "Other"; 309 distinct operators in total).

View data
Main public charging point operators (309 distinct operators), broken down by power bracket: IZIVIA, 17,882, Bouygues Energies & Services, 16,940, Power Dot France, 14,113, LIDL France, 10,689, Freshmile, 10,513…
OperatorTotalSlow (≤ 7,4 kW)Accelerated (7,4–22 kW)Fast (22–150 kW)Ultra-fast (> 150 kW)
IZIVIA17,8825,0245,9415,978939
Bouygues Energies & Services16,9404,17856511,843354
Power Dot France14,11362,9777,2683,862
LIDL France10,68906,6193,402668
Freshmile10,5131,5277,5271,304155
Electra8,19808591,5105,829
TotalEnergies Charging Services7,7094,5241,1738361,176
GROUPE INDIGO7,4227,12529520
TotalEnergies Marketing France6,3023,2638057401,494
EASYCHARGE5,660373,6921,84586
Allego5,65102,0041,7651,882
E-Totem5,5445543,1621,462366
Tesla4,752008113,941
SPIE CITYNETWORKS4,5115922,3791,366174
TESLA France SARL4,5090004,509
ENGIE Vianeo4,0754561,8594741,286
Greenflux4,0164741,8774791,186
IONITY3,8130501,0842,679
QOVOLTIS3,7532153,4325749
Citeos Mobilité Electrique Paris - Cogelum IDF3,695112,68798710
Other (289 operators)76,8786,00237,14123,09010,645

Source: Fichier consolidé des bornes de recharge pour véhicules électriques (Etalab). Publicly accessible charging points declared under the IRVE scheme and consolidated by Etalab, excluding the private fleet (home, closed company premises).

Methodology and licence

Scope
Charge points open to the public, declared under the IRVE schema and consolidated by Etalab (~100k charge points). Excludes the private fleet (homes, closed company sites) and undeclared points.
Regional breakdown
The region is derived from the department (extracted from the municipality's INSEE code, 2016 administrative boundaries). Points without a usable code (some overseas collectivities, missing code) are excluded from the regional breakdown but still counted in the national total.
AC / DC classification
A charge point is classed as "fast charging" (DC) if it offers a Combo CCS or CHAdeMO connector, and AC otherwise (Type 2 or domestic socket). The criterion is the connector type rather than a power threshold, which would produce false positives/negatives (high-power three-phase AC versus low-power DC).
Time cumulation
The monthly cumulative counts, month by month, the charge points whose commissioning date falls in that month. It is not a history of successive snapshots of the network, but a reconstruction from the declared commissioning date of points still listed today. Points commissioned and then removed before the current consolidation therefore don't appear.
Power brackets
Brackets of declared rated power: Slow ≤ 7.4 kW, Accelerated 7.4–22 kW, Fast 22–150 kW, Ultra-fast > 150 kW. Independent of the AC/DC classification by connector type.
Fast-charging threshold (100 kW)
A separate threshold counts charge points with declared rated power ≥ 100 kW, the usual definition of "fast charging" in market barometers. It situates the fully electric vehicle fleet against the public fast-charging network, independently of the bracket split shown in the "Charge-point power" chart.
Department matching (postal code fallback)
When the municipality's INSEE code is missing or cannot be matched, the department is inferred from the 5-digit postcode in the station address (first 2 digits, 3 for overseas). Corsica exception: 20xxx postcodes cannot reliably distinguish Corse-du-Sud (2A) from Haute-Corse (2B), so those points stay unmatched rather than being assigned arbitrarily.
Operators
Breakdown by operator (operator name, or brand name when missing), with normalised labels (roaming suffix removed, case harmonised). The top 20 operators by number of charge points are detailed, split by power bracket; the rest is aggregated into "Other".
Licence
Licence Ouverte / Etalab 2.0, published by Etalab / transport.data.gouv.fr (Fichier consolidé des bornes de recharge pour véhicules électriques)